1. Assignment Overview
Closed-loop chilled water system flushing and hydronic balancing works at Kingdom Arena in Riyadh for Professional Facility Management (PROfm). Work prepared the chilled water distribution network for clean operation and balanced flow rates across main headers, branches, and cooling coils.
2. Scope of Work & Deliverables
- Inspection of chilled water piping loops, flushing bypasses, strainers, and air release vents across the venue
- Closed-loop water flushing advocacy, strainer blowdown, and verification of water cleanliness prior to coil connection
- Differential pressure and flow rate measurement across circuit balancing valves (DRVs) and PICVs using calibrated hydronic manometers
- Proportional adjustment of balancing valves to achieve scheduled chilled water flow rates (GPM / L/s) at AHUs and terminal units
- Submission of certified Hydronic Flushing & Balancing Report with final valve settings and pump operating readings
3. Field Challenges & Engineering Solutions
Large-Span Venue Distribution
Long chilled water header runs across the arena required methodical air venting and staged branch balancing to ensure remote air handling units received full design water flow.
Fast-Track Event Schedule
Field teams worked extended shifts in coordination with PROfm to complete flushing and balancing within the venue readiness window.
4. Key Achievements & Verified Outcomes
- Closed-loop CHW network
- Flushed
- Design GPM verified
- Balanced
- Hydronic TAB report