1. Assignment Overview

Execution of HVAC ductwork modification, mechanical installation, and post-installation air balancing works (HVAC Works at Yanbu & Riyadh Buildings) in Riyadh – Yanbu for SYSCON. Completed in accordance with approved shop drawings and verified with calibrated airflow measurements.

2. Scope of Work & Deliverables

  • Pre-work site survey of existing ductwork layout, ceiling clearances, and equipment connections
  • Fabrication, supply, and installation of modified GI ductwork, volume control dampers, and ceiling air terminals
  • Application of thermal insulation and vapour-barrier sealing across newly installed duct sections
  • Proportional air balancing of modified supply and return branches using a calibrated digital capture hood
  • Submission of final air balance test sheets and completion sign-off to the client

3. Field Challenges & Engineering Solutions

Integration with Existing HVAC Network

New branch duct transitions and damper installations were sized and balanced to maintain design static pressure across existing connected zones.

Turnkey Mechanical & TAB Delivery

Combining duct modification and calibrated TAB under one team ensured immediate verification of room airflows upon completion.

4. Key Achievements & Verified Outcomes

Duct & mechanical works
Completed
Post-work airflow verified
Balanced
Handover test record