Hydronic Balancing Works — Global Suhaimi Facility

Hydronic Balancing · Global Suhaimi · Dammam

Hydronic Balancing·Job #26/1/1092/1·Dammam, KSA·2026
Hydronic Balancing Works at Global Suhaimi, Dammam

1. Assignment Overview

Chilled water hydronic flow measurement and balancing works (Hydronic Balancing Works — Global Suhaimi Facility) in Dammam for Global Suhaimi. Field engineers measured and adjusted water flow rates using calibrated ultrasonic flow meters and digital differential pressure gauges to match approved design schedules.

2. Scope of Work & Deliverables

  • Survey of chilled water headers, riser branches, circuit balancing valves (DRVs), and terminal cooling coils
  • Verification of strainer cleanliness, air venting, and full-open status of isolation and motorized control valves prior to measurement
  • Connection of calibrated digital hydronic manometers and ultrasonic clamp-on flow meters to record baseline flow rates (GPM / L/s)
  • Proportional adjustment of manual balancing valves and verification of PICV pre-settings to bring branches within ±10% of design flow
  • Recording of chilled water pump suction/discharge pressures, total head, and motor amperage in the final Hydronic Balancing Report

3. Field Challenges & Engineering Solutions

Hydraulic Circuit Verification

Balancing began at the index (highest-resistance) circuits and progressed proportionally across risers so adjustments did not starve remote cooling coils.

Calibrated Hydronic Instrumentation

All flow and differential pressure readings were logged with traceable digital manometers and ultrasonic flow sensors.

4. Key Achievements & Verified Outcomes

Hydronic tolerance met
±10%
Ultrasonic & DP gauges
Calibrated
Hydronic test report
Complete