HVAC Commissioning Works at GCP-04 Package-31
Commissioning & Controls · SYSCON · Jafurah

1. Assignment Overview
Pre-commissioning checks, air distribution verification, and functional HVAC testing at Gas Compression Plant GCP-04 (Package-31) in Jafurah for SYSCON. Conducted in accordance with approved project mechanical submittals and industrial site safety requirements.
2. Scope of Work & Deliverables
- Pre-commissioning mechanical inspection of installed AHUs, condensing units, extract fans, and ductwork at GCP-04
- Verification of electrical starter panels, motor rotation, running amperages, and fan RPM against nameplate ratings
- Airflow measurement and proportional balancing across supply diffusers, return grilles, and fresh-air intakes
- Verification of building pressurization differentials and control interlocks
- Preparation and submission of HVAC pre-commissioning and test records to SYSCON
3. Field Challenges & Engineering Solutions
Industrial Site Access & Safety
Field work within the active Jafurah Package-31 construction zone followed strict industrial PPE, JSA, and permit-to-work procedures.
System Readiness Verification
Mechanical and electrical pre-start checklists were completed prior to energizing fan systems to ensure clean filters, intact duct runs, and open dampers.
4. Key Achievements & Verified Outcomes
- Package-31 facility
- GCP-04
- Mechanical & airflow checks
- Verified
- Handover test dossier
- Complete