1. Assignment Overview

Pre-commissioning checks, air distribution verification, and functional HVAC testing at Gas Compression Plant GCP-04 (Package-31) in Jafurah for SYSCON. Conducted in accordance with approved project mechanical submittals and industrial site safety requirements.

2. Scope of Work & Deliverables

  • Pre-commissioning mechanical inspection of installed AHUs, condensing units, extract fans, and ductwork at GCP-04
  • Verification of electrical starter panels, motor rotation, running amperages, and fan RPM against nameplate ratings
  • Airflow measurement and proportional balancing across supply diffusers, return grilles, and fresh-air intakes
  • Verification of building pressurization differentials and control interlocks
  • Preparation and submission of HVAC pre-commissioning and test records to SYSCON

3. Field Challenges & Engineering Solutions

Industrial Site Access & Safety

Field work within the active Jafurah Package-31 construction zone followed strict industrial PPE, JSA, and permit-to-work procedures.

System Readiness Verification

Mechanical and electrical pre-start checklists were completed prior to energizing fan systems to ensure clean filters, intact duct runs, and open dampers.

4. Key Achievements & Verified Outcomes

Package-31 facility
GCP-04
Mechanical & airflow checks
Verified
Handover test dossier