Controls & Commissioning Works at GCP-01 & GCP-04 Package-31
Commissioning & Controls · SYSCON · Jafurah

1. Assignment Overview
Execution of HVAC controls verification, instrumentation loop checks, and commissioning support across Gas Compression Plants GCP-01 and GCP-04 (Package-31) in Jafurah for SYSCON. Work focused on validating control panel logic, damper and valve actuator responses, and functional sequence operation against approved project schematics.
2. Scope of Work & Deliverables
- Point-to-point continuity and I/O signal verification for HVAC control panels at GCP-01 and GCP-04
- Calibration checks and range verification for duct and room temperature, humidity, and differential pressure sensors
- Stroke testing and fail-safe position verification for motorized fire/smoke, fresh air, and volume control dampers
- Functional sequence testing of duty/standby unit changeover, alarms, and emergency shutdown interlocks
- Compilation of signed controls loop test sheets and commissioning records for consultant sign-off
3. Field Challenges & Engineering Solutions
Site Permit & LOTO Coordination
All panel testing and field actuator checks at GCP-01 and GCP-04 were conducted under industrial permit-to-work and electrical Lockout/Tagout (LOTO) controls in coordination with SYSCON site engineers.
Control Sequence Verification
Field setpoints, staging timers, and pressurization differentials were verified directly against approved Package-31 cause-and-effect matrices and control narratives.
4. Key Achievements & Verified Outcomes
- Plant packages covered
- GCP-01 & 04
- Control loops verified
- I/O & FPT
- Test sheets submitted
- Complete