TAB Works at Administration, Training & Maintenance Centre, 2nd Industrial Area
Testing, Adjusting & Balancing (TAB) · SANKYO · Jubail

1. Assignment Overview
Third-party HVAC Testing, Adjusting and Balancing (TAB) carried out for TAB Works at Administration, Training & Maintenance Centre, 2nd Industrial Area in Jubail (Client: SANKYO). All supply, return, and exhaust air systems were proportionally balanced using calibrated digital instrumentation to meet approved mechanical design schedules.
2. Scope of Work & Deliverables
- Verification of system readiness, filter condition, damper accessibility, and approved mechanical design schedules
- Baseline and final operating measurements on air handling units, fan coil units, and ventilation fans (CFM/L/s, ESP, RPM, Amps)
- Proportional air balancing across all supply diffusers, linear slot diffusers, return grilles, and exhaust valves using calibrated flow hoods
- Identification and documentation of any site airflow restrictions or mechanical snags for rapid contractor resolution
- Delivery of final stamped TAB Report containing as-found and final balanced readings, fan data sheets, and instrument calibration certificates
3. Field Challenges & Engineering Solutions
Proportional Branch Balancing
Terminals were balanced iteratively starting from the index circuit on each branch to achieve design airflow within ±10% tolerance without excessive damper throttling.
Traceable Handover Documentation
Every terminal grille and unit reading was cross-referenced to the project layout drawings and accompanied by valid laboratory calibration certificates.
4. Key Achievements & Verified Outcomes
- Balanced to design criteria
- ±10%
- Digital TAB instruments
- Calibrated
- Stamped TAB report issued
- Complete