TAB Works — Jizan Substation

Testing, Adjusting & Balancing (TAB) · Alfaneyah EM Co. Ltd. · Jizan

Testing, Adjusting & Balancing (TAB)·Job #26/1/1091/1·Jizan, KSA·2026
TAB Works at Jizan Substation, Alfaneyah EM

1. Assignment Overview

Third-party HVAC Testing, Adjusting and Balancing (TAB) and room pressurization verification for TAB Works — Jizan Substation in Jizan (Client: Alfaneyah EM Co. Ltd.). Work verified that switchgear halls, control rooms, transformer/relay rooms, and battery rooms achieved design cooling airflows and safety ventilation rates.

2. Scope of Work & Deliverables

  • Pre-balancing review of approved substation HVAC drawings, equipment schedules, and room pressurization matrices
  • Duct Pitot-tube traverses and terminal capture hood measurements across supply diffusers, return grilles, and fresh-air intakes
  • Proportional adjustment of main and branch volume control dampers (VCDs) to balance airflows within project specification tolerances
  • Measurement and adjustment of positive room pressurization differentials (Pa) in switchgear and control rooms to prevent dust ingress
  • Verification of dedicated battery room exhaust fan flow rates and compilation of the final stamped Substation TAB Report with calibration certificates

3. Field Challenges & Engineering Solutions

Substation HSE & Electrical Clearance

All testing inside high-voltage substation buildings was executed by safety-inducted engineers under strict electrical permit-to-work and LOTO procedures.

Switchroom Pressurization & Battery Exhaust

Fresh-air make-up dampers and relief paths were balanced alongside supply fans to maintain positive room pressure while verifying critical hydrogen-extract airflow in battery rooms.

4. Key Achievements & Verified Outcomes

HV facility HVAC verified
Substation
Airflow & Pa balanced
±10%
Substation TAB dossier
Certified