Supply & Installation of Air Grille — ACE Insurance Office
HVAC Modification & Works · Carrier · Al Khobar

1. Assignment Overview
Execution of targeted ceiling air distribution modification works (Supply & Installation of Air Grille — ACE Insurance Office) in Al Khobar for Carrier. Included ductwork connection adjustments, terminal grille installation/relocation, and post-work airflow verification.
2. Scope of Work & Deliverables
- Site inspection above false ceiling to verify existing flexible duct routing, plenum connections, and ceiling grid layout
- Supply and installation of new ceiling air grille with plenum box, flexible duct connection, and volume control damper
- Thermal insulation sealing and vapour-barrier taping of modified duct connections to prevent condensation
- Airflow measurement and damper adjustment at modified terminals to confirm balanced air delivery
- Site housekeeping, ceiling tile reinstatement, and client completion sign-off
3. Field Challenges & Engineering Solutions
Occupied Commercial Office
Ceiling and duct modifications were executed cleanly with dust protection sheeting and coordinated outside peak banking/office hours.
Airflow Verification
Following grille installation/relocation, terminal airflow was measured and balanced to prevent drafts or dead zones in the modified rooms.
4. Key Achievements & Verified Outcomes
- Grille & duct modification
- Completed
- Terminal airflow checked
- Verified
- Client handover note
- Signed Off