Installation of Pipe Flexible Connectors & Insulation Repair — Battoyoor Tower
HVAC Modification & Works · Acciona · Al Khobar

1. Assignment Overview
Mechanical replacement of chilled water pipe flexible connectors and thermal insulation repair at Battoyoor Tower in Al Khobar for Acciona. Work eliminated piping vibration transmission and restored vapour-sealed thermal insulation.
2. Scope of Work & Deliverables
- Isolation, depressurization, and localized draining of the affected chilled water piping section
- Removal of deteriorated pipe flexible connectors and installation of new rated flexible connectors with aligned flange bolts
- Hydrostatic leak check upon refilling and venting of the chilled water riser/branch connection
- Repair and replacement of damaged closed-cell elastomeric thermal insulation with protective cladding and vapour-seal adhesive
- Inspection sign-off and restoration of normal chilled water circulation
3. Field Challenges & Engineering Solutions
Controlled System Shutdown
Chilled water isolation and draining were executed within a scheduled maintenance window to minimize cooling interruption to tower tenants.
Condensation Prevention
All replacement insulation joints were fully vapour-sealed to prevent surface sweating under high Eastern Province humidity.
4. Key Achievements & Verified Outcomes
- Pipe flexible connectors
- Replaced
- Pressure & insulation check
- Leak-Free
- Site handover sign-off
- Completed